Arrow diagram is also called as _______ diagram

A) Activity Network diagram or Critical Path diagram or PERT Diagram
Explanation: The Activity Network Diagram is also known as the PERT diagram or the critical path diagram. It evaluates the time it takes from the beginning of a process to the end of a process and determines where there is slack time, and what parts of the process can be improved in relation to time

Showing Answers 1 - 1 of 1 Answers

Arrow diagram is one of the Project schedule network diagram formed by Arrow diagramming method.(ADM). It uses Arrows to represent activities and connects them at nodes to show their dependencies
This is also knows as "Activity on Arrow"(AOA)
It uses only finish-to-start dependencies and can require dummy activities to define all logical relationships correctly..


Amar